Progress Report #2

November 02, 2005_news_38_1Good progress is being made on the trestle rebuilding.

Trestles 15 and 14 are now complete and trestle 13 is well underway and will be finished by the end of November.

There have been some delays on trestle 2 but it is proceeding well now and should be finished by the end of November.

For more pictures on the trestle rebuilding visit our Photo Gallery.

Rock work at the trestle 3 site is nearly finished. If trestle 2 is finished in good time, so equipment can cross it, we hope to make a start on trestle 3 construction before the winter shutdown.

In the meantime, design work is continuing for trestles 4 and 5 on the Ruth side and for trestles 10 and 11 on the Myra side. These are to be rebuilt in 2006.